Glendale Community College

Master Planning Updates

3/02/07: Master Planning Update #11

Master Planning Updates #1-10

If you have not had the opportunity, please read Master Planning Updates #1 (June 17, 2003), #2 (August 29, 2003), #3 (October 16, 2003), #4 (July 27, 2005), #5 (January 30, 2006), #6 (March 13, 2006), #7 (April 24, 2006), #8 (July 6, 2006), #9 (September 1, 2006), and #10 (December 1, 2006). These updates are archived on this web site.

Quick Master Planning Summary

For those with limited time, the following is a quick, USA Today style update on Master Planning projects (the links provide shortcuts to the respective sections in the report below):

  • The Student Union is almost complete. Phase IV (South side meeting rooms) began in early October and will be finished March 12, 2007. A Grand Re-opening is scheduled for 1:30-4:00 p.m. March 28, 2007 and rooms will be available for scheduling in April.
  • GCC North. The College reviewed 100 percent Construction Documents mid-February. CORE Construction will provide a final cost (Gross maximum Price) next Wednesday (March 7). Off-site improvements along Happy Valley Road are designed and out for bid.
  • Life Science Building. The consultants, Gould Evans met with the Life Science Planning Team on January 31st to preview a three dimensional presentation of the new Life Science Bldg. A college-wide viewing of this presentation will be scheduled for the week of March 5th. The planning team completed a review of Design Development documents with Gould Evans earlier this week. Gould Evans is now working on Construction Documents which should be available to the College within six weeks.
  • Chiller Plant Upgrade Project. This project will remain largely invisible to the campus community but is necessary as we bring the new Life Science and Applied Technology buildings on line. The upgrade replaces a forty year old, lower capacity chiller and two cooling towers. The second of two new new towers was installed February 7. The upgrade will improve energy efficiency and enhance our conservation practices. Another part of this project is the upgrade of the small office area used by our HVAC technicians. The new office will provide insulated walls to better protect our staff from the plant noise and expand the area to provide better small item storage. See Chiller Plant Upgrade Gallery for views of the work in progress.

For additional information on GCC projects, please read on.

Student Union Remodel

Construction is now 98 percent complete! Jokake Construction commenced work on Phase IV October 16, 2006 and will finish on March 12th. This phase will complete remodel efforts begun in April 2006. Phase IV adds five scalable meeting rooms where the old dining area once stood. Looking north, this 5,400+ sf area can be divided into equal thirds by two collapsible walls, producing three, 1,800+ sf meeting rooms. The western most room can be further divided on an east-west axis into thirds, also by two smaller collapsible walls, producing three 500-600 sf meeting rooms. In a nutshell, this area of the Student Union will be capable of supporting small, medium and large events, up to five events simultaneously. The drawing below, not to scale, depicts the scalable phase IV meeting room area.

Drawing NOT TO SCALE. top of the drawing is north.

Rooms named after palm species, symbolic of the main campus. When all walls (those depicted with green dashes) are collapsed, Palm Court will be realized.

Equally important to the employees in the Enrollment Center, especially the ladies: your concerns have been heard. A curved, low-rise ramp will be added to the west end of the building, exactly like the ramp on the east end. No more having to negotiate grass, gravel and low walls in heels.

Finally, the Student Union will receive new energy efficient glazing and landscaping. Completion of the entire project is scheduled for March 12, 2007 or earlier.

Please take a moment and see Student Union Construction Gallery #4 to view construction underway in Phase IV and the use of the Student Union (phases I-III) by our students.

GCC North

Below is a schematic from the Master Plan showing the proposed construction to be completed by 2044. Those buildings in the northeast part of the site (upper right) and identified with letters (a-f), are to be constructed as part of phase one (completion 2008) and will support the College until the next bond cycle (typically every ten years). Moving counterclockwise around the site, phase two is in the northwest quadrant (2014-2024), phase three in the southwest quadrant (2024-2034), and phase four in the southeast quadrant (2034-2044).

Proposed Build-out of GCC North 2006-2014

Open larger version of GCCN Proposal

Final Construction Documents(CD) have been reviewed. CORE Construction will complete costing of the project and provide a Gross Maximum Price by March 7. Construction is scheduled to begin in April-May 2007. The project will add three new buildings: Instruction ( Classrooms/Labs/Offices ), Information ( Library/Media/Computer Commons ), and Student Services ( Business Services/Student Life/Cafeteria/Fitness Center ), plus a Central Plant, a total of 65,000 square feet to the existing 20,000 sf site. Buildings are designed to support future programmatic growth and the Central Plant capable of up-scaling to support the future three phases of construction (2014-2044).

Please take a moment to open photos of the new fence added to the property to better preserve the desert site, and the vegetation salvage project designed to preserve native Ironwoods, the climax species for this site.


Looking north to Ludden Mountain, Instruction and Information buildings in foreground.


Computer Commons, from inside the Information building.

Life Science Building

On January 31st the Life Science Planning Team met with Gould Evans (Architect Consultant) to preview a three dimensional tour of the new Life Science Bldg. Graphics that depict the proposed facility may be viewed in Life Sciences Building Construction Gallery #1. Design Development (DD) documents were reviewed by the planning team last week, and an extremely informative presentation by Gould Evans will be scheduled for the College at large during the week of March 5th. Please look for an upcoming announcement regarding presentation dates and times.

The new facility will be GCC's first three story structure and will house the Biology, Psychology and Nursing Departments. The proposed facility will contain 6 general purpose classrooms (@36-48 student capacity), 72 offices and common work spaces, a central Lab Prep Area, nine Biology labs, an Animal Research lab, four Nursing Observation pods and large (@120+ student capacity) room dividable into three smaller rooms. The facility will also contain a working greenhouse and small cafe. The Gould Evans design places the cafe, greenhouse, Nursing pods, large dividable classroom, and four general classrooms on the first floor, offices and conference rooms on the second floor, and all lab facilities, two classrooms and mechanical plant on the third floor. Construction is still expected to begin in July-August 2007 and the building prepared for instruction at the beginning of the Spring semester 2009.


Open Life Sciences Building Construction Gallery #1 to view several depictions of the planned facility.

Glendale Community College Bond Projects Schedule 2004-2014

In order to help employees and community members track progress of GCC Main and North projects, the following is an abbreviated timeline of actions associated with each project. Details of three projects in progress: Student Union Remodel, new Life Science Bldg., and expansion of the GCC North site are discussed further in this document.

Project Ed Specs Development Consultant Selection Design and Construction Documents Development Construction Begins (estimate) Substantial Completion (estimate) Punch List - Occupy
SU* Jan –
Mar 2005
ART Jul 2005
Jokake Sep 2005
Aug 2005 –
Feb 2006
Apr 2006 Mar 12, 2007 Mar –
Jun 2007
Life Science Bldg. (formerly N Bldg.)* Apr 2005 –
Feb 2006
Gould Evans May 2006
DPR May 2005
Sep 2006 –
May 2007
Aug 2007 Oct 2008 Nov –
Dec 2008
NW Bldg. Mar –
Jun 2007
Jul –
Aug 2007
Sep 2007 –
May 2008
Jun 2008 Aug 2009 Sep –
Dec 2009
B Bldg. Jul –
Sep 2007
Oct –
Nov 2007
Nov 2007 –
Jun 2008
Jul 2008 May 2009 Jun-Aug 2009
T1 Bldg. Jul –
Sep 2008
Oct –
Nov 2008
Dec 2008 –
Jul 2009
Aug 2009 Aug 2010 Sep –
Dec 2010
T3 Auto (some T2) Jul –
Sep 2009
Oct –
Nov 2009
Dec 2009 –
Jul 2010
Aug 2010 Aug 2011 Sep –
Dec 2011
Old LS/NU Bldg. Dec 2011 –
Feb 2011
Mar –
Apr 2011
May –
Nov 2011
Dec 2011 Oct 2012 Nov 2012
F&W Bldg. Sep –
Dec 2010
Jan –
Feb 2011
Mar –
Nov 2011
Dec 2011 Feb 2013 Mar –
Jun 2013
Vogel Via Gaucho Entrances* Aug –
Sep 2005
Oct –
Nov 2005
Dec 2005 –
Feb 2006
Mar 2006 Oct 2006 N/A
Chiller Plant Upgrades 1 Nov 2006 –
Jan 2007
Feb –
Mar 2007
Apr –
Aug 2007
Sep 2007 Jan 2008 Feb 2008
GCC North* Mar –
Sep 2005
RNL Design Jan 2006
CORE Feb 2006
Jan –
Nov 2006
Dec 2006 Mar 2008 Apr –
Jul 2008

1 Upgrade of the Chiller Plant is a District project designed to prepare the campus infrastructure to support new buildings.

* Planning is currently underway for several projects (highlighted in light green ), and each is discussed further in this document.

Questions - Comments

Your input and questions concerning any of the College's bond projects is always welcome. If you have questions or ideas, please share them with the College. You can do this by clicking on the following email link. Questions and concerns will be addressed as expeditiously as possible, and where appropriate, shared with other readers in future Master Planning Updates.

E-mail Questions - Comments

Summary

In closing, let me express the College's sincere appreciation to those who have shared ideas, expertise and time toward the master planning process, development of the College's Project Lists, educational specifications, review of proposals and selection of architects and construction firms. Every attempt has been made to be inclusive, and the College will continue this approach as we plan, design and construct each project. If anyone desires a copy of documentation for any specific project, please email me and I will provide a copy or direct you to an on-line link. Please stay engaged. With your continued participation and ideas, GCC will become what we dream.

Charles F. Jeffery
Acting Vice President - Administrative Services and Planning


In this site:

We welcome feedback.

Content revised 1/30/08


Maricopa Community Colleges